Asphalt Plant Construction
- Caravan Park Ground Works
- Redstone Rd, Narberth
Design & build of a new asphalt plant for A&C Aggregates
ITH Construction was tasked with the design and build of a new asphalt plant within the existing industrial zone of Pembroke Dock. The scope of works included:
- Design of a whole new site.
- Initial site preparation.
- Planning & Approval.
- Reduction of levels within the main structural area.
- Installations of service ducts, electric cables and water mains.
- Installation of foul sewer drainage and pumping station
- Installation of surface water attenuation tanks.
- Reinforced concrete retaining walls, weigh bridge support structure and asphalt plant foundations, including temporary support and reinforcement.
- Installation of the asphalt processing plant superstructure, including steel framed building.
- Construction of a material storage building, reinforced concrete slab and precast concrete retaining walls.
- Installation of fibre reinforced slab to the yard and roadway and finishing to the required technical specifications.
- Commission & Testing.